Monitoring Analytics expects PJM’s capacity auction to add $6.3 billion to customer and business bills across 13 states and Washington, DC, through 2029 because of data-center demand. Yet the grid operator has cut its demand forecast because some projects, including data centers, lack firm service or construction commitments.
Key takeaways
- Monitoring Analytics expects PJM’s capacity auction to add $6.3 billion to customer and business bills across 13 states and Washington, DC, through 2029.
- Arizona Public Service proposed a 45% electricity-rate increase for data centers.
- New York paused new environmental permits for data centers above 50 MW for up to one year.
- PJM reduced its summer 2027 peak-demand forecast from about 164 GW to about 160 GW.
- Oracle moved completion dates for some OpenAI data centers from 2027 to 2028, citing labor and material shortages.
New York has paused new environmental permits for large data centers. AI-data-center opposition is becoming a fight over who pays for power before it becomes a broad veto on capacity. For a developer or tenant, the scarce asset is firm, deliverable electricity on a date the tenant and its financing can accept.
PJM’s auction made projected demand a public bill
PJM has to prepare for demand before customers switch on their equipment; its recent capacity auction put a price on that preparation. That protects reliability, but a proposed campus can impose costs before it produces usable compute. Residents do not need to oppose a particular building to contest that allocation.
Arizona Public Service proposed a 45% electricity-rate increase for data centers, arguing that they should pay their fair share. The proposal addresses how much of the cost of serving a large new load its owner should bear. New York’s moratorium goes further, blocking new environmental permits for data centers above 50 MW for up to one year. Neither a proposed rate nor a permit pause describes how much power has permanently left the national construction pipeline, but both give public opposition a decision point.
A restricted boundary does not measure a stopped project
SemiAnalysis mapped more than 300 local moratoriums encompassing jurisdictions with about 20 GW of planned capacity. It attributed roughly 1,525 MW of delay to local moratoriums; including New York’s action, it estimated that direct project-level policies had delayed about 2.3 GW nationwide. The 20 GW measures capacity planned inside restricted jurisdictions, while the smaller figures measure delays attributed to specific policies. Subtracting one from the other would treat every plan inside a boundary as a project that was ready to proceed and then stopped.
A developer can put megawatts on a site plan before securing power or construction commitments. By late 2025, the U.S. tally of capacity that was built, underway, planned or stalled had exceeded 80 GW. Those categories belong in a view of the buildout, but they do not promise the same delivery date. A permit authorizes work under specified conditions; it cannot establish that the grid will serve every proposed rack when a tenant needs it.
Opposition still has consequences beyond the direct-policy estimate. Data Center Watch reported at least 75 projects worth about $130 billion blocked or delayed by opponents in the first quarter of 2026. That count measures projects and investment exposure, not policy-attributed megawatts. Bernstein’s assessment that only about 35% of the planned U.S. pipeline was credible points to a broader problem: many announced projects may fail to arrive for reasons other than a moratorium.
PJM is testing whether an applicant can actually take service
PJM cut its summer 2027 peak-demand forecast from about 164 GW to about 160 GW because some projects, including data centers, lacked firm service or construction commitments. The revision did not identify four gigawatts of data centers that local governments had blocked. It removed demand PJM could not yet treat with the same confidence as a committed load.
The operator also proposed requiring large data centers to bring their own generation or curtail electricity use to reduce the risk of a large-scale outage. FERC approved orders intended to handle data-center power requests in 90 days while adding requirements for AI hyperscalers. A faster decision on an application cannot itself supply generation at a strained hour. PJM’s proposed choices instead ask what a campus can do when the shared grid cannot serve every claimed load at once.
A data center needs power, cooling and computing equipment working as one system; surplus racks cannot compensate for electricity that does not arrive. As the grid approaches its limits, a developer must establish the conditions under which its load can remain connected.
A delayed power date changes the tenant’s contract
SynMax found that almost 40% of U.S. data centers due in 2026 faced delays, with major Microsoft and OpenAI projects likely to finish more than three months late. That measure covers execution slippage, not just policy action, which is why it can be much larger than SemiAnalysis’s 2.3 GW direct-policy estimate without contradicting it. A tenant buying compute for a particular start date cannot substitute a permitted campus that finishes a quarter later.
Oracle pushed completion dates for some data centers it is building for OpenAI from 2027 to 2028, largely because of labor and material shortages. Electricity is one dependency among several: crews and equipment have to reach the same site on a compatible schedule. When any one of them slips, the developer has to revisit the revenue start date behind its project-finance case.
Advanced campuses reveal what the pipeline counts conceal
SemiAnalysis projected more than 50 GW of data-center capacity additions in 2027 and identified more than 24 GW across 40 campuses in advanced stages. The projection is not delivered supply, and “advanced” is not a guarantee. It does, however, separate projects with substantial work underway from capacity that exists mainly as an intention. Nscale acquired a 2,250-acre West Virginia campus with plans for roughly 8 GW of compute by 2031; acquiring the land did not fix a date for serving that load.
Frequently asked questions
What share of the 20 GW inside moratorium jurisdictions has been directly delayed by policy?
Using the piece’s nationwide direct-policy estimate, about 2.3 GW divided by 20 GW is roughly 11.5%. That is not a cancellation rate: the 20 GW is planned capacity within restricted jurisdictions, while 2.3 GW is delay attributed to specific policies.
How large was PJM’s summer 2027 forecast reduction?
PJM lowered the forecast by about 4 GW, from roughly 164 GW to 160 GW. That is approximately a 2.4% reduction from the original forecast, tied to projects lacking firm service or construction commitments.
How much larger is the nationwide direct-policy delay estimate than the local-moratorium estimate alone?
The difference is about 775 MW: roughly 2.3 GW nationwide less 1,525 MW attributed to local moratoriums. The piece says the broader estimate includes New York’s action, but it does not assign the entire difference to New York.
What electricity rate will Arizona Public Service ultimately charge data centers?
The piece does not give a final approved rate or an effective date. It identifies a proposed 45% increase, not an adopted tariff.
Capacity figures measure different stages of the buildout
| Measure | Figure | What it counts |
|---|---|---|
| Moratorium jurisdictions | About 20 GW | Planned data-center capacity in jurisdictions covered by more than 300 local moratoriums |
| Local-moratorium delay | Roughly 1,525 MW | Delay attributed to local moratoriums |
| Nationwide direct-policy delay | About 2.3 GW | Delay attributed to direct project-level policies, including New York’s action |
| U.S. capacity tally, late 2025 | More than 80 GW | Capacity built, underway, planned or stalled |
| Projected 2027 additions | More than 50 GW | SemiAnalysis projection for data-center capacity additions |
| Advanced campuses | More than 24 GW across 40 campuses | Capacity SemiAnalysis identified as in advanced stages |
New York can pause a permit, Arizona Public Service can propose a different rate, and PJM can demand a firmer account of how a campus will operate. Each decision reaches a different part of the same construction schedule. On the site plan, the racks have addresses. At the substation, they still need a date.