In October 2026, Google signed a 3,590-MW agreement with Constellation Energy in PJM. Only about a quarter is described as new nuclear supply, and Google’s data centers still need a way to take the power.
Key takeaways
- PJM reduced its summer 2027 peak-demand forecast from about 164 GW to about 160 GW after excluding some proposed projects without firm service or construction commitments.
- Google has demand-response agreements with five U.S. utilities covering up to 1 GW of potential load reduction during grid peaks.
- Constellation proposed a $1.6 billion restart and refurbishment of Three Mile Island in September 2024.
- Amazon’s 20-year, 690-MW Constellation agreement was paired with more than $3 billion of planned investment at a Maryland nuclear plant.
- Meta’s 20-year purchase from Constellation’s Illinois plant begins in mid-2027, when a 10-year state subsidy expires.
Developers are routing around the grid connection
AI data-center developers are pursuing on-site power plants to bypass overloaded grid connections. Building generation beside a facility introduces its own permitting and supply-chain problems, but the choice reveals what a conventional power purchase cannot guarantee: a place for the load to connect on the required schedule.
PJM supplied a useful check on announced demand when it cut its summer 2027 peak forecast from about 164 GW to about 160 GW. Some proposed projects, including data centers, lacked firm service or construction commitments. PJM did not establish that those projects would never be built. It declined to count every proposed megawatt as committed load.
That distinction matters to a nuclear seller. A plant can have a buyer for its output while a data-center project still needs grid service, construction, and a way to consume power at the relevant times. The cited reporting does not establish interconnection rights or delivered incremental capacity for Constellation’s announced expansions.
Constellation’s buyers are backing different kinds of capacity
In September 2024, Constellation proposed spending $1.6 billion to restart Three Mile Island and selling its output to Microsoft under a reported 20-year, 835-MW agreement. A restart is a capital project with a named customer, not an operating plant created by signing a contract.
Amazon’s 20-year agreement for 690 MW came with more than $3 billion of planned Constellation investment to increase capacity at a Maryland nuclear plant. Google then contracted for 3,590 MW in PJM; about one-quarter is described as new nuclear energy. Google says 890 MW of new reliable nuclear capacity is planned over five years. The rest of the contracted volume should not be mistaken for 3,590 MW of new generation.
Constellation appeared in three raw articles from the first seven days of 2026’s fourth quarter, matching its count for all of 2024’s third quarter. Reporters covered its restart in 2024 and its Amazon and Google deals in October 2026, a difference the matching counts conceal.
Other buyers draw an equally important line between keeping existing output under contract and adding supply. Meta agreed to buy power from Constellation’s Illinois plant for 20 years starting in mid-2027, when its state subsidy expires. Meta also signed a 20-year agreement for more than 2,600 MW from three Vistra plants while supporting prospective TerraPower and Oklo projects. The Vistra plants’ existing output still flows into the grid; only uprates add generation. These arrangements serve different purposes even when each carries a nuclear label.
A 20-year term does not disclose who bears the risk
Constellation’s restart and Maryland investment plans each have a named, long-duration buyer. For location-bound assets that take years and substantial capital to develop, that pairing gives a generator a reason to consider investment. It does not, by itself, tell a lender what happens if construction slips or the buyer’s demand changes. Financial Times reporting in August described lenders, insurers, and underwriters limiting their exposure to the novel risks of U.S. AI data centers; the related AI data-center financing problem extends to the power needed to run them.
The cited reporting does not disclose these power agreements’ prices, take-or-pay obligations, termination rights, credit support, or allocation of restart and delivery risk. Long duration establishes neither a financeable demand guarantee nor protection against a delayed plant.
Microsoft reportedly froze roughly 1.5 GW of data-center projects planned for 2025 and 2026 and walked away from more than 2 GW of non-binding contracts. Microsoft could leave those non-binding contracts, but the cited reporting does not establish that it can leave its Constellation agreement. A generator cannot treat a buyer’s entire projected computing pipeline as an irrevocable power need.
Compute dispatch becomes part of the power calculation
Google has separately signed demand-response agreements with five U.S. utilities covering up to 1 GW of load reduction during grid peaks. The cited record does not say those agreements cover the facilities associated with Constellation’s PJM supply. They do establish a second operational requirement for a large power buyer: obtaining electricity and reducing consumption when the grid needs relief.
Stratechery argued in May that agentic inference could change infrastructure requirements because speed matters less when a human is not waiting for each response. That creates a possible scheduling lever, not proof that any particular workload can move. An operator with fixed power commitments must still decide which jobs can run steadily, which can wait, and which require power regardless of a grid peak.
Frequently asked questions
When will Google’s planned 890 MW of new nuclear capacity actually enter service?
The cited material says the 890 MW is planned over five years, but it does not disclose unit-by-unit in-service dates, construction milestones, or regulatory approvals. That leaves the delivery schedule unverified.
Which Google data centers will receive power under the 3,590-MW PJM agreement?
The cited reporting does not identify the facilities tied to the agreement or establish their interconnection rights. A PJM supply contract alone does not show that a particular data-center site has firm grid service.
What will Google pay, and what happens if the nuclear expansion is delayed?
The reporting does not disclose the price, take-or-pay provisions, termination rights, credit support, or allocation of restart and delivery risk. Those terms determine how much commercial protection either side has if construction or demand changes.
Can the announced megawatt figures be converted into annual electricity available to data centers?
Not from the information provided. That calculation would require operating assumptions such as plant output, outage schedules, transmission availability, and when the data centers are able to take the power.
Constellation’s long-term buyer agreements
| Buyer | Announcement date | Contracted power | Term | Associated generation investment or new supply |
|---|---|---|---|---|
| Microsoft | 2024-09-21 | 835 MW | 20 years | $1.6 billion proposed for the Three Mile Island restart |
| Amazon | 2026-10-01 | 690 MW | 20 years | More than $3 billion planned to boost capacity at a Maryland nuclear plant |
| 2026-10-07 | 3,590 MW | Not disclosed | About 890 MW of new reliable nuclear capacity planned over five years; about 25% of contracted supply described as new nuclear energy |
If plant output, firm grid service, and movable computing work cannot meet at the same place and time, a contracted megawatt does not become a usable GPU-hour. Constellation can sign for supply measured in gigawatts; the scarce unit is the megawatt-hour a data center can actually take.