In June 2026, Digital Realty moved to buy a majority stake in three fully leased Northern Virginia data centers in a deal valuing the assets at $7.8 billion. The public reporting does not disclose the megawatts assigned to each building or their energization dates.
Key takeaways
- Digital Realty announced on June 29, 2026, that it planned to acquire a majority stake in three fully leased Northern Virginia data centers from Blackstone-managed funds at a $7.8 billion asset valuation.
- PJM reduced its summer 2027 peak-demand forecast in January 2026 from roughly 164 GW to 160 GW.
- Anthropic’s reported Kentucky lease is worth roughly $19 billion over 20 years and is expected to provide about 400 MW in the second half of 2027.
- Data-center customers were reported in October to be seeking more than $5 million per day in late-delivery fees, versus $1 million per day in the spring.
- Global Energy Monitor counted more than 97 GW of proposed U.S. gas-fired generation linked explicitly to data centers in the 2025 pipeline, up from 4 GW in 2024.
AI is turning the data center from a real-estate category into a power-delivery business: customers need megawatts they can use on a date they can plan around, supported by grid service, cooling, backup systems, and permission to operate.
The two Blackstone deals cannot be priced alike
In December 2023, Digital Realty and Blackstone formed a $7 billion venture to develop ten data centers across four campuses in Frankfurt, Paris, and Northern Virginia. In June 2026, Digital Realty moved to acquire a majority stake in three fully leased Northern Virginia facilities from Blackstone-managed funds. The public accounts do not establish whether those facilities belonged to the earlier venture.
The first figure describes a development program; the second is an asset valuation for leased properties, not the amount Digital Realty will pay for its stake. Available reporting also leaves interconnection rights and power-supply arrangements undisclosed. Rent, tenant quality, location, and scarcity may all contribute to the valuation. The two figures cannot yield a like-for-like cost trend or a price per usable megawatt.
Customers have begun putting a price on late power
Anthropic signed a roughly $19 billion, 20-year lease for a Kentucky data center expected to have about 400 MW of capacity and to begin delivering power in the second half of 2027. That date matters to a tenant planning when it can use the capacity; the reported expectation does not, by itself, establish a delivery guarantee.
October reporting described data-center customers demanding more than $5 million a day in late-delivery fees, up from $1 million in the spring. Those demands are not terms of Digital Realty’s Virginia leases. They show the financial question an investor needs the leases to answer: if capacity arrives late, who bears the cost of waiting?
PJM’s forecast cut is a screen, not a verdict on these sites
In January 2026, PJM Interconnection cut its summer 2027 peak-demand forecast from roughly 164 GW to 160 GW because some proposed projects, including data centers, lacked firm power service or construction commitments. PJM did not identify Digital Realty’s three buildings. Its revision is a regional forecast adjustment, not a measurement of power available at any one property.
PJM’s screen shows what evidence matters before proposed load enters a dependable forecast. A tenant or investor assessing the Virginia properties would need their own service commitments and commissioning schedules; applying a share of PJM’s 4 GW reduction to them would invent a shortfall the grid operator did not report.
Cooling can interrupt service after power arrives
In November 2025, a cooling failure at a CyrusOne facility disrupted CME Group and global futures markets. CME was not an AI-training customer, but the outage shows how an operating data center can lose service even after it has a grid connection.
AI hardware puts a different load on that system. Nvidia’s GH200 passed 1 kW in 2023 as manufacturers increasingly adopted direct liquid cooling; in 2026, Google was reported to be seeking liquid-cooling equipment amid tight supply. For a tenant planning dense racks, the operator has to demonstrate that the building’s cooling design can support the intended hardware, alongside its electrical supply.
Bringing power on-site adds an approval problem
PJM proposed that large data centers bring their own generation or accept curtailment. Global Energy Monitor counted more than 97 GW of proposed US gas-fired generation explicitly linked to data centers in the 2025 pipeline, up from 4 GW in 2024. Those figures describe proposed plants, not available power. Building one would add equipment procurement, fuel, and approvals to a developer’s schedule.
Local opposition has already changed development plans. More than 24 US data-center projects were blocked in January 2026 alone. Digital Realty, QTS, and NTT Data warned that the industry was doing a poor job countering opposition; QTS later abandoned its portion of a 2,100-acre Virginia campus after years of opposition and legal challenges. A developer seeking to solve a grid wait with a new plant must also clear the approvals for that plant.
Frequently asked questions
What percentage of the Virginia data centers will Digital Realty own?
The reported transaction specifies only a majority stake. It does not disclose Digital Realty’s exact ownership percentage or the remaining ownership split.
Who are the tenants in the three fully leased Northern Virginia facilities?
The public deal accounts cited in the piece describe the sites as fully leased but do not identify the tenants.
When is the Digital Realty transaction expected to close?
No closing date is stated in the reporting summarized here. The available accounts describe a planned acquisition rather than a completed purchase.
What happens if power or capacity delivery is delayed at the Virginia sites?
The lease provisions are not public. Reported demands for late-delivery fees elsewhere are not identified as terms of Digital Realty’s Virginia leases.
Do the three acquired facilities belong to Digital Realty and Blackstone’s 2023 development venture?
That cannot be confirmed from the public accounts. The 2023 venture covered 10 data centers across four campuses in Frankfurt, Paris, and Northern Virginia, but reporting does not establish whether these three properties were part of it.
Power-delivery milestones around the deal
- November 2025 — A cooling failure at a CyrusOne facility disrupted CME Group and global futures markets.
- January 2026 — PJM cut its summer 2027 peak-demand forecast from roughly 164 GW to 160 GW; more than 24 U.S. data-center projects were also reported blocked that month.
- June 29, 2026 — Digital Realty announced plans to acquire a majority stake in three fully leased Northern Virginia data centers at a $7.8 billion asset valuation.
- Second half of 2027 — Anthropic’s Kentucky data-center lease is expected to begin delivering about 400 MW of capacity.
The $7.8 billion valuation may reflect rent, location, and scarce space. If any of the leased space is still awaiting power or cooling, its delivery terms will decide who bears the wait.